Manufacturing and industrial

Takeaways

Triage downtime and tighten maintenance to lift OEE and cut repair time.

Key findings

  • Quick-fix triage absorbed ~40% of incidents within 30 minutes.
  • MTTR fell to 4.8h after spares list + standard work.
  • OEE at 82% driven by uptime; quality stable.

Signals

OEE %
82%
from ~60% baseline
MTTR
4.8 hours
from 7h baseline
Unplanned downtime hrs
560 hrs/yr
down 30% from ~800

What we would do next

  • Kanban the top-20 spares with min/max levels.
  • Daily 10-minute tier meeting around Andon events.
  • Predictive PM on Press-1/2 using vibration trend.